This month, relatively quietly, President Trump invoked the Defense Production Act to get America to ship more missiles. The memo was filed on June 11th and found that conditions exist which “may pose a direct threat to the national defense.” It pointed at limited production capacity, fragile supply chains with long lead times, and production bottlenecks across the munitions industrial base. Of course, it was all over the news.
Most of the headlines repeated the same story that we’ve heard since the war with Iran started. “We fired off too many missiles and the shells are thin, so now we have to build more.” All of this is true. But this moment is particularly interesting.
Over the past year, I’ve spent most of my day inside the planning and scheduling systems of defense manufacturers. What’s different about this moment is that the government’s first move wasn’t to write a check or break ground with a new plant in our industrial base. We’ve been spending capital in that way for months. Instead, President Trump invoked Section 708. This is the provision that lets competing primes sit in a room and coordinate.
They were allowed to share information and plan together without tripping antitrust law. The Pentagon’s own Michael Cadenazzi described it as not just allowing, but asking companies to work together in a way where they may “essentially collude.”
The key context here is that, rather than push more spending into the system, President Trump felt it necessary to encourage coordination and address the true problem in our defense industrial base: currently, information doesn’t flow.
Money is a very slow lever
The instinct when a stockpile runs dry is usually to spend. And when spending is coming, the defense leadership on the Hill is pitching hundreds of billions to replenish our stockpile. That’s a good thing. We need it for deterrence. But money buys capacity on a multi-year delay. It’s an almost parallel problem to the money being spent on the datacenter buildout for AI. A lot of the production capacity won’t land till the late 2020s or even 2030. Replacing what we’ve burned through could take years, not months.
The solid rocket motor base, which is the literal long pole in the tent for most of these missiles, has shrunk from six U.S. manufacturers to two since the 1990s. You cannot conjure a qualified SRM line with a wire transfer because qualification alone runs years.
So if money is the slow lever, then the question is, what is the fast one?
The fast lever is making the industrial base you already have, the factories you already have, much more legible. You should know today where your bottleneck sits, and what’s been clear is that tribal knowledge almost never answers that question in the way we quite expect it to. Knowing what’s the long lead item, if you expedite it this quarter, unlocks three downstream items next quarter. Knowing what your existing plants could actually produce if they were sequenced well, before you spend a dollar on new ones, buys capacity. And that idle capacity sitting on the table right now is not used because the system can’t see itself.
We are very good at counting what we spent, but we are remarkably bad at seeing what we already have; most glaringly, we are remarkably bad at seeing what the bottleneck is as we think two or three moves ahead after solving the present one.
There’s a revealing tension throughout this whole episode, which started June 11th. Some have waved away the shortage of a manufactured story and insisted that the stockpiles are fine. Privately, however, in the White House, the worry is real enough to produce a Defense Production Act invocation. I’m interested in the structural fact underneath it.
Seeing the chess board
One think-tank analysis put expedited interceptors at roughly half of several critical inventories, and those estimates become public debate precisely because the authoritative real-time number does not exist in a form that anyone specifically can act on. Our core problem, I argue, is the fact that we can’t see the board at all and we need ground truth, everywhere.
The part that keeps me up at night is that the Iran campaign, by the standards of what we planned for, was a manageable draw, by most accounts, of our stockpile. The scenario that this entire industrial-based conversation is really about is the fight in INDOPACOM, which would demand surging production an order of magnitude faster against an adversary, in China, that is, by most honest assessments, out-producing us on ships, drones, and munitions today.
You do not surge a system you cannot see into. You cannot sequence long lead times you’ve never modeled. You cannot coordinate across primes who each hold a slice of the picture in a spreadsheet that nobody else can open. Today is not time for panic.
I’d say that the 2026 munition scare is a fire drill, but we should treat it like a serious one. We shouldn’t panic by capacity. Instead, we should finally instrument the base, so that when capacity does arrive it lands on the actual constraint instead of the assumed one. We shouldn’t just be funding new companies, we should be figuring out how to ramp production within the companies where we’ve mastered it already.
The real action
The Defense Production Act is a tool from 1950. We used it back then to address a problem that is increasingly about information flow. In 2026, we’ve used it to address a problem that is about information flow and planning across a complex, brittle, and distributed network and supply chain.
I’m not criticizing the invocation of the Defense Production Act this month. I think bringing together the primes is the right instinct. It’s an observation that the next edge in the defense industrial base won’t come from one new factory. It will come by making the whole industrial base legible, mappable, simulable, and plan-able, so the surge is an engineering problem with a known answer that is verifiable rather than a guess we make under pressure.
I should be honest that I’m not a neutral observer here. The company that I co-founded built exactly this kind of software for defense and manufacturing, so discount me accordingly, but you don’t have to buy anything from anyone to take the underlying point seriously.
The lesson of the last few weeks isn’t that America forgot how to build missiles. It’s that we’ve been running one of the most consequential production systems in the world, largely in the dark. The war with Iran turned the lights on for just a moment. The question coming out of June is whether we keep them on.